Scheduling, management and coordination (OPC): an organised site, deadlines met

In plain words

On a building site, several contractors follow one another: mason, electrician, plumber, painter… If one falls behind or arrives at the wrong time, all the others are held up. Our role is to organise who works when, monitor progress and act before problems become expensive.

What we do for you

  1. The schedule (scheduling)

    We draw up the detailed timetable for design and works, and identify the tasks that cannot slip without delaying completion (the “critical path”).

    What you gain: a realistic, secure completion date.

  2. Follow-up (site management)

    We lead site meetings, measure actual progress and request extra resources or adjustments as soon as a delay looms.

    What you gain: problems are dealt with immediately, not at the end of the works.

  3. Organisation (coordination)

    We organise site logistics and the interfaces between trades, so that teams can work at the same time, without getting in each other’s way and safely.

    What you gain: less wasted time, fewer defects.

  4. The end of the works (handover)

    Before the keys are handed over, we inspect the works with you and list the defects to be fixed (the “snags”), then follow up their correction.

    What you gain: compliant premises, delivered without disputes.

A real example

Modernising and extending a pharmacy in Touraine, without ever closing

Background
This project was led by our founder, before Adim-Nete was founded. The pharmacist had his pharmacy and an adjoining unit used for selling and fitting prostheses.
The project
Open up the load-bearing wall between the two units and modernise an ageing pharmacy.
The constraints
Working during the day, in a pharmacy that stayed open to the public, by splitting the works into successive phases. And taking into account the patients present in the area still in operation.
The result
All unforeseen site issues were absorbed by the schedule, with no delay. The works lasted 10 weeks, at a controlled cost: only the extra works requested by the client along the way were added to the budget. The pharmacist was satisfied with a project completed without closing his pharmacy.